Wildfire Fuel Treatment Update HWY 39

Hwy 39 Wildfire Fuel Reduction Project

Works are progressing nicely on the highway 39 fuel reduction treatments. Crews have completed 90% of works on TU 13, 70% on TU 14, 50% TU 9, 25% on TU 8 and just started on TU 5. The manual crew will be taking a much-deserved break over the Christmas holidays and returning on the 5th of January. Mechanical works will continue through a portion of the break to allow them to get ground ready for manual crews.

 

We hope you all have a happy, safe and healthy holiday season!

 

Updates are posted on the Mackenzie Wildfire Advisory Committee website, broadcast by CHMM 103.5 FM radio station, and shared via the Facebook page.