Skip to content

Paving plan 2026

click to enlarge

The District of Mackenzie’s 2026 Paving Plan is now underway, with construction activities expected to take place from mid-June through early July.

Tentative Work Schedule

  • June 16–19: Recreation Centre concrete work
  • June 22: Milling on Nechako, Stuart, Robinson, McIntyre, Grayling, and Skeena (sections)
  • June 23: Milling on Skeena, Selwyn, Centennial (A, B, C), Chichouyenily, Cicada Rd, and Public Works Yard
  • June 24–25: Paving on Centennial areas, Chichouyenily, Cicada Rd, Selwyn, and surrounding locations
  • June 26–July 1: Paving on Skeena (sections), Recreation Centre, Stuart, Nechako, Robinson, McIntyre, and Grayling

What to Expect

  • Temporary traffic delays and detours
  • Limited on-street parking in work zones
  • Short-term access impacts to driveways
This schedule is tentative and may change due to weather or operational requirements. The District will notify residents of any significant changes or delays.
We appreciate your patience as these important road improvements are completed.