2025 Paving Program Schedule Update : October
An update on the 2025 Paving Program Schedule for the month of October*:
October 2
Nechako Dr. - Paving - Completed
October 3
Portage Cres. - Paving - Rained Out
October 4
Portage Cres. - Paving - Completed
October 5
Ralston Dr - Paving - To be completed October 8
October 6
Stuart Dr & Babine Dr - Water line break repair - Paving - Completed
*Please note schedule can change based on weather